Chilling of Blast Furnace – its causes and recovery Mar31

Tags

Related Posts

Share This

Chilling of Blast Furnace – its causes and recovery


Chilling of Blast Furnace – its causes and recovery

The chilling of a blast furnace is a very serious happening during the operation of a blast furnace. The revival of a chilled blast furnace is a big herculean task and it takes a very long time and needs a lot of patience to bring back the furnace to normal condition. In case of hearth chilling, it is not possible to tap liquid slag and hot metal, since the temperature in lower part of the blast furnace becomes very low and the connection between the tap hole and tuyere is lost. This is due to the solidification of the liquid slag which obstructs the liquids flow to the hearth.

The chilling of blast furnace is varying from minor to very severe. The chilling of a blast furnace is minor when connection between tuyere and tap hole is lost but there is sufficient heat in the hearth. When the hilling becomes more severe, the hot metal also starts solidifying. In case of most severe chill the hot metal in the hearth also gets solidified. A severe chill in a blast furnace is shown in Fig. 1

 Severe chill in a blast furnace                     Fig 1 Severe chill as seen from a tap hole

Causes of blast furnace chilling

Normally blast furnace should give warning signals before furnace shows the symptoms of chilling. The warning signals will consists of

  • Reduction in wind volume and slow burden movement due to furnace running cold
  • Very frequent hanging and slipping in the furnace
  • Temperature of tapped hot metal and liquid slag is lower than normal
  • Tapped liquid slag is viscous and not moving in the runner.
  • Water coming out from the tap hole
  • Blocking of tuyeres and blow pipes with slag or slag-metal mixture
  • Excessive build up of hot metal and slag in the furnace due to either insufficient draining of the hot metal and slag during tapping and/or delay in opening of the tap hole.
  • Very less coke in the dead man area

When the furnace starts giving warning signals it is necessary to take remedial actions to avoid approaching for a furnace chilling. The corrective actions are many but it is advisable to run the furnace on the hotter side by increasing the coke in the charge.

The solidification of liquid slag can start when the conditions inside the blast furnace favours it. The main conditions are temperature (1350-1390 deg C) and slag composition (ratio of CaO + MgO, SiO2 and MgO). FeO (unreduced iron oxide) also plays an important role. Factors affecting the viscosity of liquid slag are important since the viscous slag is difficult to drain from the furnace. It should be remembered that in a cold furnace the slag is having composition where the viscosity and the melting temperatures are higher. The melting temperature is higher than that of iron. Hence when the blast furnace starts showing symptoms of chilling then it is always very important to drain the blast furnace from liquid slag as much as possible, though it a difficult thing at this condition of the blast furnace. The chilling of the furnace can be due to the following reasons:

i)            Excessive water leakage

ii)           Out of specification furnace feed materials (Raw materials)

iii)         Vast fluctuations in the quality of the raw materials

iv)          Instruments and measuring devices are either not calibrated properly or malfunctioning.

v)           Blast furnace operator is not able to read properly the happening inside the furnace from the data available to him.

vi)          Operator either not reacting or reacting late to the problems notices during the operation.

vii)        Early warning sign are not reported to higher ups

viii)       Violations of technological discipline with respect inspection of water leakage, cast house practice and blanking of tuyeres etc.

ix)          Lack of experience of operating personnel

x)           Unprepared furnace stoppages due to sudden break downs of key equipments requiring major repair and long time for repair. These include charging system. Hot blast system and gas collecting and cleaning system.

xi)          Tap hole or hearth break out needing a long time for recovery

Actions needed to avoid severe chilling of the blast furnace

The normal practice of a blast furnace operator when the furnace start the signs of near chill situation is to continue operations at reduced wind volume while trying to improve the excavation of liquid slag and hot metal by drilling and/ or oxygen lancing. If draining is not successful then hot metal and liquid slag continues ti get build up inside the furnace. It is very likely that the furnace has suffered with hanging and slipping during this period. At this stage when the furnace condition has seriously deteriorated additional charging of the fuel though desirable but may not be of much help. In case situation is not improved it becomes necessary to stop the furnace for safety reasons since postponement of such decision for long can results into high liquid levels inside the furnace leading to burning tuyeres, coolers and blow pipes which will stop the furnace and will make the furnace very unsafe. The furnace situation in such situation will normally be as follows:

  • The opening of the tap hole is not possible either by drilling or lancing
  • Tuyeres and blow pipes are filled with slag
  • Some tuyeres are having solidified material in front of them
  • The permeability of the furnace has deteriorated and the layered structure of the stack is disturbed due to the frequent slips.
  • Slag/ metal has accumulated up to half way of the bosh or even higher
  • Remedial actions taken of increasing the fuel in the charge gets disturbed due to process upset
  • Additional water leakage takes place due to the process upset.

In the present day practice of running the furnace with fuel injection at the tuyere it is more difficult to restart the furnace after a few days if the furnace has been stopped with unprepared burden. For restarting the furnace after a few days of unplanned stoppage it is necessary that enough coke is available in front of the tuyeres.

It is always desirable that remedial actions for the recovery should start as soon as the symptoms of the furnace chilling are visible. It is advisable not to experiment at this stage and take the help of an expert. However in the extreme case when it becomes very difficult to recover then the furnace needs to be raked out. Such a situation will arise when the furnace contains excessive amount of solidified slag, there is a lot of water ingress and very little coke remains in the deadman zone.

Recovery plan

For making a good recovery plan it is essential to the furnace status at the start of the recovery. The furnace status can be known by the following steps

i)            The burden composition along with the coke rate is to be estimated

ii)           The slag and the hot metal levels inside the furnace is to be estimated

iii)         To know the composition of the burden materials and slag as well as the burden ratio

iv)          To determine whether all the water leakages in the furnace has stopped.

v)           To identify the tap hole which is better for the recovery to start

vi)          To determine the coke rate and the Basicity of the burden to be charged.

vii)        To clean all the tuyeres and the blow pipe and to plug them

viii)       To determine the number of tuyeres with which the furnace should restart.

If the hearth has been drained out empty as during the case of a heath break out then the furnace recovery is easier as compared to when the furnace is full of slag and water. Furnaces with process related problems are more difficult to revive.

The process of recovery

For the recovery of a chilled furnace it is necessary to re-establish connections between tap hole and tuyeres. Maximum heat is to be brought into the furnace to remelt the solidified slag and metal. It is also necessary to drain the melted materials. These steps are to be built into the plan. The things are not to be hurried up and next step is to taken after assessing the success of the previous step. Here operators experience and judgment is very important.

The tap hole – tuyere connection can be re established by hand lancing or using thermal lances. This is the traditional method. In this method the working environment is hot, very harsh and full of hazards. The amount of heat which can be introduced by this method is small and is generally enough to remelt slag in a narrow passage from tuyeres to the tap hole. But since no air is blown in the furnace the furnace continue to cool down. Further furnace cannot be started without the connection between tap hole and the tuyere. Once the connection between the tap hole and tuyere is made the furnace is started with air blown in one or two tuyeres only. It must be done very carefully and with ample care to avoid re blocking the open connection. Adjacent tuyeres are opened after stabilizing blowing in these one or two tuyeres and if the operation conditions are favorable.  For this a continuous monitoring is needed for the open tuyeres by the visual observations through the peep holes.

It is important that during the recovery process tuyeres does not get opened on its own. This will start production of liquids at these tuyeres resulting in burning of tuyeres, blow pipes and coolers. This will cause un necessary delays during first critical delays of the recovery. The tuyeres are to be opened only as per plan and hence proper plug in of the tuyeres after cleaning is very important.

The furnace recovery is very slow by this traditional method. However now a days for faster recovery oxy fuel technology is being used. In this technology the connection between tap hole and tuyere is achieved by introducing a large amount of heat below the tuyeres by burning oxygen and fuel gas introduced in the furnace through lances that are drilled 3.5-4.5 meters inside the hearth. Most of the hat is generated by burning of the coke of deadman zone with oxygen.

Conclusion

Since the chilling is a very serious type of the furnace outage and its potential consequences are very large. It is very essential there should be standard procedure for furnace chilling in every plant and the operators are well trained in the recovery process.